Four Laning of Oddanchatram – Madathukulam section of NH-209 (New NH-83) of 45.38 kms (Design Ch. Km 29.000 to Km. 74.380) on Hybrid annuity mode in the State of Tamil Nadu.
| Name of SPV | KNR Palani Infra Private Limited |
|---|---|
| Concessioning Authority | National Highways Authority of India (“NHAI”) |
| Project Location | Tamil Nadu |
| Appointed Date | 5th October 2020 |
| Construction Period | 730 Days |
| PCOD | PCOD achieved on 2nd September 2022 |