Four laning with paved shoulder of Porbandar ‐ Dwarka section of NH-8E (Ext.) from km 356.766 (design chainage km. 379.100) to km 473.000 (Design Chainage km 496.848).
SPV | Porbandar Dwarka Expressway Private Limited (PDEPL) |
---|---|
Authority | National Highways Authority of India (NHAI) |
Project Location | Gujarat |
Appointed Date | 12th Feb 2018 |
Construction Period | 1095 Days |
PCOD | 18th Apr 2020 |
COD | 13th Oct 2021 |